Otahuhu Station and Half Moon Bay Ferry Terminal
| Client | Auckland Transport |
| Location | Auckland |
| Services | Advisory, Engineer to the Contract |
| Value | $28 million/$6 million |
Otahuhu Station and the Half Moon Bay Ferry Pier are two of Auckland Transport’s recent projects upgrading dated facilities.
Inovo performed the Engineer to the Contract role for Auckland Transport for both projects, providing expert advice and guidance for the resolution of claims and disputes, including NZ3910.
Otahuhu Station is fully-integrated bus-train station, linking the existing rail platform with two new bus platforms and a terminal building via an elevated concourse. The Half Moon Bay pier provides safer, more convenient connections between ferry services and existing bus services, and plays a pivotal role in supporting new bus services that form part of the new bus network for east Auckland.